Quiz Summary
0 of 19 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 19 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 19
1. Question
You have been criticised that certain specifications in your scope statement do not pass the test for SMART objectives. What are SMART objectives?
CorrectIncorrect -
Question 2 of 19
2. Question
What is Risk Management?
CorrectIncorrect -
Question 3 of 19
3. Question
Which of the following statements is true about risks?
CorrectIncorrect -
Question 4 of 19
4. Question
Beta is the Project Manager of a Road construction project. During a project review, Beta realizes that one particular risk has occurred. To take appropriate action against risk that has happened, Beta needs to refer to which document?
CorrectIncorrect -
Question 5 of 19
5. Question
Andrew is a Project Manager for Green Valley project. A risk management plan has been prepared for the project. Which of the following should Andrew do next?
CorrectIncorrect -
Question 6 of 19
6. Question
Changes to the Information Distribution process should trigger changes to project management plan and the ___________________ management plan.
CorrectIncorrect -
Question 7 of 19
7. Question
Items at the lowest level of a Work Breakdown Structure are also called:
CorrectIncorrect -
Question 8 of 19
8. Question
You are explaining the importance of Work Breakdown Structure (WBS) to your project team members. In this context, all the following statements about Work Breakdown Structure(WBS) are correct EXCEPT:
CorrectIncorrect -
Question 9 of 19
9. Question
The entire process of a project may be considered to be made up on number of sub process placed in different stage called the __________________________.
CorrectIncorrect -
Question 10 of 19
10. Question
Following is (are) the component(s) of risk management:
CorrectIncorrect -
Question 11 of 19
11. Question
An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed.
CorrectIncorrect -
Question 12 of 19
12. Question
Which of the following is NOT one of the steps in the risk management process?
CorrectIncorrect -
Question 13 of 19
13. Question
Detailing all identified risks, including descriptions, category, and probability of occurring, impact, responses, contingency plans, owners and current status is called:
CorrectIncorrect -
Question 14 of 19
14. Question
In which of the following project phases is the project schedule developed?
CorrectIncorrect -
Question 15 of 19
15. Question
Which of the following can cause a communication barrier?
CorrectIncorrect -
Question 16 of 19
16. Question
Which of the following is not considered as a risk in project management?
CorrectIncorrect -
Question 17 of 19
17. Question
An example of the risk involved in software development is:
CorrectIncorrect -
Question 18 of 19
18. Question
Which of the following is NOT a PERT event?
CorrectIncorrect -
Question 19 of 19
19. Question
The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?
CorrectIncorrect